Here is a high level timeline for the scheduled work:
- Demolition of Maintenance Building - Work began on January 11 with window and cladding removal. The structure is scheduled to be demolished between February 8 and March 1, with backfill completion by March 5.
- Demolition of smoke stack – work begins February 1 and ends February 2.
- Demolition of Unit 2 – Work is scheduled to begin on January 25 with demolition scheduled to happen between April 6 and May 3 and backfill completion by May 7.
- Demolition of Unit 4 ̶ Work is scheduled to begin on February 22 with demolition scheduled to happen between June 1 and June 14 with backfill completion by June 18.
- TD Commons Completion (South Portion) – Work is scheduled from June 21 to August 9.
- Stoke Street Extension – Work is scheduled from August 10 to September 23.
- Grounds Building Demolition – Work is scheduled from September 24 to October 13
We will be providing more details as they become available.
For more information, please contact redevelopment.feedback@camh.ca.